Deck waterproofing remains critical to a bridge’s structural integrity for its design life, explains Cliff Weston, director of Stirling Lloyd    
To properly maintain deck waterproofing there must be a willingness to look at solutions based on whole-life costing rather than just short-term initial costs. There are lessons to be learned from examples of prematurely failed infrastructure due to a focus on initial short-term costs. 
Not only this, any maintenance required once a bridge has been built could mean putting it out of service, causing disruption to the economy and the local community, as well as having environmental impacts. The overall challenge is to carry out the maintenance work while keeping the bridge in service at all times, completing the works in the shortest possible time avoiding unnecessary costs and disruption. 
Effective long-term protection should be a given benefit of any quality waterproofing system, after which speed and ease of the application are, more often than not, the key requirements for waterproofing application. Eliminator, 
On one recent contract a requirement was to open the waterway – where the bridges span – at least every hour, which reduced the available productive working hours and consequently outputs per day. However, due to the system’s speed and ease of application, the contractor was still able to coat 2000m2 per day. This helped ensure fast progress on the project, disruption was minimised and the bridges being returned to service on schedule. 
Always looking to innovate, Stirling Lloyd’s in-house research and development team developed Bond Coat 3, a durable bond coat to be part of the Eliminator system, which is highly resistant to damage and pick-up by vehicles including site traffic in hot weather and is easily cleaned where contamination occurs. This addition to the Eliminator systems enables the asphalt binder course to be applied immediately or, if programming dictates, allows the system to be trafficked until surfacing takes place. 
 Production of an initial long-term asset management plan can help keep  bridge maintenance to a minimum. However, it will still involve some  refurbishment work to ensure bridge longevity and to keep traffic moving  as much as possible. 
Replacing  asphalt pavement and waterproofing on a bridge involves a number of  processes, some of which can be affected by unpredictable events. Once a  deck is exposed to the elements, inclement weather can quickly  deteriorate a surface, leading to unforeseen repairs which might be  costly in terms of money and project scheduling. This could severely  disrupt asphalt production and placement.
Undertaking  the works in small sections is one solution. But this can be very  expensive and will usually prolong traffic delays and increase  disruption to users for an extended period.
An  example of a contract in the US that carried out refurbishment work  quickly and efficiently was Fast 14. The project involved 10 weeks of  work to replace 14 bridges on the busy I-93 highway near Boston. It was  aptly named, as the work would have taken over four years using  traditional methods of working and materials.
Following  inspection in 2010, the concrete decking and steel beams were found to  be failing on the 14 ageing bridges. The Massachusetts Department of  Transportation looked to the Federal Highways Accelerated Bridge  Construction Programme for ideas on how to keep disruption to a minimum.  The following work sequence was decided after a review of the available  refurbishment methodologies and materials that could fulfil it and  comparing it to the possible environmental and economic costs of years  of traffic congestion associated with the alternative. 
After  Friday evening rush hour, traffic flow was changed on the I-93. One of  the 14 bridges was then dismantled, new prefabricated concrete bridge  panels were put in place and joined together, with rapid setting  concrete diaphragms followed by the application of temporary road  markings. The new temporary bridge was open by the time Monday morning  commuters were on the road. 
On  a subsequent weekend the Eliminator waterproofing was installed. This  involved the spray application of two coats of membrane in two  light-coloured contrasting coats to help ensure correct and complete  coverage during the required night time application. To give a high  friction anti-skid surface, aggregate was broadcast into the second coat  of membrane, providing a temporary trafficable wearing surface. Again  the bridge was returned to service for Monday morning rush-hour. 
When  possession could be taken again, the surface of the membrane, which was  undamaged by the regular heavy traffic flow, was simply brushed to  remove any debris and dirt. Stirling Lloyd’s proprietary bond coat was  then applied to provide a bond for the asphalt pavement that followed.
    
Consequently  each ‘new’ bridge was placed and protected over three weekends with no  disruption to weekday traffic. Weekend disruption was a small price to  pay compared to what would have been regular road closures over four  years with potential total closure of the interstate.  
We  need to look to progressive models such as this to ensure the effective  provision of long-term protection to some of the UK’s bridges where the  consequences of daytime closures are unthinkable. Through the use of  new initiatives and innovations, including those developed by UK  companies such as Stirling Lloyd, we can ensure that the structural  integrity of bridges is protected for the intended design life with  minimal disruption to road users.